The Template Collective Blog

Project management templates… and more

Monthly Archives: February 2017

Uncategorized

Manage the Schedule for Small Projects

Manage the Schedule for Small Projects

All projects need a schedule. If you have a small project perhaps the schedule is a simple checklist or Excel spreadsheet. As projects get larger they need more formal scheduling templates and tools.

The processes you use to manage a schedule also vary depending on the size of the project. Large projects need a lot of schedule management rigor. Small projects can use a lighter process. The following steps can be used to mage the schedule of a small project.

  1. Review the schedule on a weekly basis.
  2. Identify activities that have been completed during the previous week and update the schedule to show they are finished.
  3. Determine whether there are activities that should be completed, but are not. Work with the individual that is assigned to the work see what is going on. Determine how much additional effort and duration are needed to complete the work and update the schedule accordingly.
  4. Evaluate the remaining work to see if the project will be completed within the original duration. You may find that even though some activities may be completing later than planned, other activities may be completing early and the overall schedule may still be okay.
  5. If your project is trending behind schedule, think of schedule management techniques you can apply to get back on schedule. Raise a schedule risk in your status report if the original deadline appears to be in jeopardy.
  6. Adjust the schedule so that it reflects the remaining work to be completed, and is as accurate as possible.

Since this is a process for a small project, it would be unusual to have major problems with the schedule. The consequences of problems on small projects are generally small as well.

Uncategorized

Define the Objectives of Your Project

Define the Objectives of Your Project

Objectives are concrete statements that describe the things the project is trying to achieve. They are included in your Project Charter. An objective should be written in a way that it can be evaluated at the conclusion of a project to see whether it was achieved. A well-worded objective will be Specific, Measurable, Attainable / Achievable, Realistic and Time-bound (SMART). (SMART is a technique for wording the objective. An objective does not absolutely have to be SMART to be valid.)

An example of an objective statement might be to “upgrade the customer service telephone system by December 31 to achieve average client wait times of no more than two minutes“.

  • Note that the objective is specific.
  • The objective is measurable in terms of the average client wait times the new phone system is trying to achieve.
  • You can assume that the objective is achievable and realistic.
  • The objective is time-bound, and should be completed by December 31.

Objectives should infer the deliverables of the project. In the prior example, the objective refers to the upgrade of the telephone system. If you cannot determine the deliverables that are created to achieve the objective, the objective may be written at too high a level. On the other hand, if an objective describes the characteristics of the deliverables (such as speed or ability to handle a specific number of users), it is written at too low a level. Characteristics tend to be more requirements statements – not objectives.

If the project is a part of a larger program, the objectives of all the underlying projects should be in alignment with the program objectives.

Objectives are important because they show a consensus of agreement between the project manager and the project sponsor on the main purpose of the project. For example, the specific deliverables of an IT project may or may not make sense to the project sponsor. However, the objectives should be written in a way that they are understandable by all of the project stakeholders.

Objectives are also valuable since they provide alignment to organization goals and strategies. Your organization should not authorize projects that do not tie to goals and strategies

The project objectives should be defined and agreed upon before the project starts. The deliverables of the project are created based on the objectives. A facilitated meeting between all major stakeholders is a good way to create the objectives and gain a consensus on them at the same time.